A capacity-limited scheme with active load management
Accepting less capacity and sharing it dynamically, trading peak performance for a scheme that can actually be built now.
Last updated 2026-09-06

What is A capacity-limited scheme with active load management?
Active load management is the answer to a very common situation: the site has some spare capacity but not enough for every charger to run at full output at the same time, and the cost or the lead time of a larger connection is unacceptable. Rather than build fewer chargers, the scheme installs the number of bays the site needs and adds a control system that shares the available capacity between them in real time. When one vehicle is charging it may receive full output. When ten are charging, each receives a share. The total drawn by the site is held below the limit the connection allows, continuously, by the system rather than by hope.
The trade being made is explicit and should be stated plainly to whoever will operate the site. Peak performance is given up. A driver arriving at a busy moment charges more slowly than the same unit would deliver on an empty site. In exchange, the scheme can be built now, at a cost the project can bear, with more bays than the raw capacity would otherwise support. For a great many applications that trade is entirely acceptable, because the vehicles are parked for hours anyway and the constraint that matters is how many cars can be served overnight, not how fast any one of them charges at six in the evening.
Management can extend beyond the chargers themselves. On most projects the system monitors total demand at the intake, so that the building's own load is taken into account and the charging allocation shrinks when the kitchen, the plant or the refrigeration is working hard. Some schemes go further and manage other flexible loads on the site as well. The critical design questions are what happens when the control system fails, how the site behaves when communications are lost, and what minimum output each vehicle is guaranteed. The behaviour of the system under failure is a design matter for the designer and the specification and is at least as important as its behaviour when everything works.
How does A capacity-limited scheme with active load management work, step by step?
- 1
Step 1: Fix the limit the site must stay below
The starting point is a hard number: the maximum total demand the site is permitted to draw. That comes from the agreed capacity of the connection, less a margin, and it is confirmed rather than assumed. The designer then decides where that limit is measured - at the intake, so that building load is included, or at the charging distribution only, which is simpler but ignores everything else the site does. On most projects measuring at the intake is the right answer, because charging load and building peak occur together far more often than optimistic modelling suggests.
- 2
Step 2: Model utilisation to size the scheme
With the limit fixed, the number of bays follows from how the site will be used. A workplace car park where cars arrive over an hour and stay eight has enormous scope for sharing. A rapid site where drivers stay twenty minutes has very little. The designer models arrivals, dwell times and energy delivered per session to establish how many bays the available capacity can genuinely serve, and what the experience looks like at the busiest hour rather than the average one. The output is a stated service level, agreed with the client, not simply a bay count.
- 3
Step 3: Specify the control hierarchy
The specification sets out how capacity is allocated: equally between active sessions, in priority order, by vehicle need, or by some combination. It sets the minimum output any connected vehicle is guaranteed, because a share small enough to be useless is worse than a queue. It states how quickly the system must respond to a change in building load. On sites with different user groups - staff, visitors, fleet - the hierarchy also encodes who gets priority, which is a commercial decision rather than a technical one and belongs to the client.
- 4
Step 4: Design the metering and communications
Active management depends on measurement. Metering at the intake and at the charging distribution provides the data the controller acts on, and the communications between the meters, the controller and the chargers have to be reliable enough to be trusted with the site's connection limit. Routes for that communication are designed and installed with the same care as the power distribution, because a control system that cannot see the site is a control system that cannot protect it. Cabling and containment for control systems is installed alongside the power infrastructure so the routes are proved once.
- 5
Step 5: Design the failure behaviour
The most important part of the design is what happens when something stops working. If the controller fails, if a meter stops reporting, or if communications to a group of chargers are lost, the site must fall back to a state that cannot exceed the connection limit. On most projects that means each charger defaults to a restricted output that is safe in aggregate even if every unit is drawing at once. The fallback arrangement, and the protective measures that sit behind it, are matters for the designer and are set out in the specification. They are not adjusted on site.
- 6
Step 6: Install the distribution and the chargers
The physical works are conventional: distribution equipment, cable routes across the site, bases and protection for each unit, and the containment for the control and communications infrastructure. All electrical work is carried out by competent qualified people, and where it involves existing live equipment it proceeds under permit. Because these schemes are usually chosen precisely because a bigger connection was unaffordable, there is a temptation to economise on the containment and the control routes. That is a false saving, since the whole scheme depends on them.
- 7
Step 7: Commission the management as well as the power
Commissioning has two halves. The electrical installation is tested and certified by competent qualified people to the designer's specification. Then the management system itself is proved, which means demonstrating that the site limit actually holds. That involves loading the site deliberately - occupying bays, running the building at high demand - and confirming that total demand stays below the limit, that allocation behaves as specified, and that the fallback state engages when communications are interrupted. A scheme that has not been tested at its limit has not been commissioned.
- 8
Step 8: Monitor, and revisit the assumptions
Once operating, the site produces exactly the data the design was guessing at: real arrival patterns, real dwell times, real coincidence with building load. That data is reviewed at a defined interval. It may show the site is comfortably within its limit and could take more bays, or that the service level at peak is worse than promised and the priority rules need changing, or that a larger connection is now justified by demonstrated demand. The management system turns an uncertain forecast into an evidence base for the next decision.
What are the benefits of A capacity-limited scheme with active load management?
- Delivers more charging bays than the raw available capacity would otherwise support
- Avoids or defers the cost and lead time of a larger network connection
- Protects the connection limit continuously and automatically rather than by procedure
- Takes the building's own demand into account when it is measured at the intake
- Produces operational data that supports a later, better-evidenced capacity decision
- Allows a scheme to be built now on sites where waiting is not commercially acceptable
What are the limitations of A capacity-limited scheme with active load management?
- Peak performance is given up, and drivers charge more slowly when the site is busy
- Poorly suited to rapid and ultra-rapid sites where short dwell times leave no scope to share
- Adds a control system, communications and metering that must be maintained and understood
- Failure behaviour must be designed carefully or the scheme becomes a risk to the connection
- Service level at peak has to be explained to the operator and to drivers, or it disappoints
- Priority rules between user groups are a commercial argument the client has to settle
What is A capacity-limited scheme with active load management best suited for?
What plant does A capacity-limited scheme with active load management need?
- Metering equipment at the intake and at the charging distribution
- Load management controller and its communications infrastructure
- Cable installation and containment plant for both power and control routes
- Small excavation plant for distribution routes within the site
- Temporary load banks or a means of loading the site for commissioning proof
- Test instruments for certification by competent qualified people
How is A capacity-limited scheme with active load management quality-checked?
- Site demand limit confirmed against the connection agreement and recorded on the drawings
- Utilisation model and the resulting peak-hour service level agreed with the client in writing
- Allocation rules, guaranteed minimum output and priority hierarchy stated in the specification
- Fallback behaviour on controller or communications failure demonstrated at commissioning
- Site proved at its limit under deliberate load, not merely energised and left
- Defined review point after a period of operation, with monitored data compared to the model