Off-Site & Modern MethodsSite-Based MMC - Tunnel Form, Jump Form, Slipform, ICF - method

Insulating concrete formwork (ICF)

Hollow insulating blocks stay in place as permanent formwork and insulation, with concrete poured into the middle.

Last updated 2026-09-05

Insulating concrete formwork (ICF)

What is Insulating concrete formwork (ICF)?

Insulating concrete formwork builds a wall out of hollow lightweight units - blocks, planks or large panels - that are dry-stacked into position, reinforced, and then filled with concrete. The units are not removed. They stay as permanent formwork and become the insulation on both faces of the finished wall. What you end up with is a reinforced concrete core sandwiched between continuous layers of insulation, with fixing points built into the units for the internal lining and the external finish.

The appeal is that one operation delivers several things at once. The structure, the insulation, the airtightness line and the formwork all arrive together, and the units are light enough to be handled without craneage on housing work. Because the insulation is continuous on both faces and the joints between units are made as they are stacked, the wall tends to perform well on heat loss and air leakage without a separate specialist trade being brought in to achieve it. The concrete core gives good sound reduction and useful thermal mass. On low-rise housing the walls of a house can go up in a matter of days, which is why ICF has found a settled place in self-build, small developer housing and increasingly in larger residential and school projects.

The control that decides whether an ICF wall is good or bad is the pour. The stacked units are light and, until the concrete is in and set, they are held in position entirely by the bracing and alignment system. Concrete pressing outwards on a light formwork face is unforgiving: too much pressure and the wall bulges, a joint bursts, or a whole panel is lost. So the pour is planned in layers, the placing sequence is controlled, compaction is done in a way that does not overpressure the face, and the bracing and alignment system is installed to the supplier's and the temporary works designer's arrangement and checked before pouring starts. The pour rate, the lift heights, the bracing and the propping are set by the temporary works designer for the particular wall and are checked immediately before each pour. The other recurring issue is that everything is buried: services, fixings and openings have to be planned in, because chasing into a finished ICF wall means cutting through insulation to reach concrete.

How does Insulating concrete formwork (ICF) work, step by step?

  1. 1

    Step 1: Design the wall and set out the module

    ICF units come in a module, and a design that respects the module wastes far less and builds faster. Wall lengths, corners, openings and floor levels are set out to suit the unit dimensions, and the designer confirms the concrete core thickness, the reinforcement and the connections for floors and roof. The route of every service and the position of every heavy fixing is decided at this stage, because both have to be accommodated in the units or cast into the core. On most projects a short unit-by-unit setting-out exercise before any material arrives pays for itself several times over.

  2. 2

    Step 2: Prepare the foundation and set the starter course

    The wall is only as straight as the base it starts from. The foundation or slab is checked for level and for line, and starter bars are positioned to match the reinforcement the designer has specified in the core. The first course is set out precisely and fixed down, because every course above follows it. Damp-proofing and the junction detail between the slab and the wall are made at this point, and the continuity of the insulation across that junction is worth as much attention as the rest of the wall.

  3. 3

    Step 3: Stack the units and build in the openings

    Units are dry-stacked course by course, interlocking as they go, with joints staggered and corners formed with purpose-made units. Window and door openings are framed with bucks that stay in place, and lintel reinforcement is positioned over them. The stacking is quick and needs no mortar, which is why the walls of a house rise so fast, but it is also the point at which every future problem is either designed out or built in. Service conduits, sleeves and fixing plates are placed as the courses go up, to the marked-up drawing.

  4. 4

    Step 4: Fix reinforcement in the cavity

    Vertical and horizontal reinforcement is placed in the cavity as the units are stacked, lapped and tied to the arrangement the designer has specified, with additional steel around openings and at corners. Because the reinforcement will be completely hidden the moment concrete goes in, it is inspected and signed off before the pour, and the record of that inspection is the only evidence that will ever exist. Spacers hold the steel in position so that it does not end up against one face when the concrete arrives.

  5. 5

    Step 5: Install bracing and alignment, and have it checked

    The bracing and alignment system is the temporary works. Vertical walers hold the wall plumb, the alignment gear lets it be adjusted, and the props hold the whole thing steady against the pressure of the pour and against wind on a large stacked but unfilled wall. It is installed to the supplier's arrangement and the temporary works designer's design, and it is inspected and signed before the concrete truck is called. Corners, openings and free ends get particular attention because they are where the face is weakest. Working platforms for the pour are part of this arrangement, not an afterthought.

  6. 6

    Step 6: Pour in controlled layers

    The concrete is placed in horizontal layers around the wall rather than filled from one point, so that the pressure on the light formwork face stays within what the design allows. The lift heights, the rate of placing and the time between layers are set by the temporary works designer and followed. Placing is usually by pump with the hose kept low to reduce free fall. Compaction is done in a way that consolidates the concrete without overpressuring the face - a matter the supplier and designer specify, not a matter of preference. Someone walks the wall continuously during the pour watching for movement at joints, corners and openings.

  7. 7

    Step 7: Check, adjust and cure

    While the concrete is still workable the wall is checked for plumb and line and adjusted on the alignment gear, because after it sets nothing can be moved. Any bulge, joint separation or leak is dealt with immediately. The wall is then left braced and undisturbed while the concrete gains strength, and the bracing is only released when the temporary works designer's criteria have been met. The insulation itself keeps the concrete warm, which helps in cold weather, but it also means the surface gives no clue about what is happening inside.

  8. 8

    Step 8: Strip the bracing and finish both faces

    Once released, the bracing comes off and the wall is ready for finishes. Internally the lining is fixed to the fixing points built into the units. Externally a render, a cladding system or a masonry skin is applied to whatever the design specifies, and the detailing at openings, at the eaves and at the base has to keep both the insulation and the weather line continuous. Services run in chases pre-formed in the insulation or in the pre-placed conduits. The finished wall records nothing of what is inside it, which is why the pre-pour inspections are the quality record.

What are the benefits of Insulating concrete formwork (ICF)?

  • Structure, insulation, formwork and airtightness line delivered in one operation
  • Continuous insulation on both faces with few cold bridges, and good airtightness achieved without a separate specialist trade
  • Light units handled by hand on low-rise work, with no craneage needed for the walls
  • Very fast erection - the walls of a house commonly go up in days
  • Concrete core gives good sound reduction, robustness and thermal mass
  • Small crews, a short learning curve and a simple, repeatable site process

What are the limitations of Insulating concrete formwork (ICF)?

  • Pour pressure is the critical control - a wall poured too fast or too high in a lift can bulge or blow
  • Everything is buried: services, fixings and openings must be planned in, and chasing later means cutting through insulation
  • Reinforcement and cavity condition are hidden the moment concrete goes in, so pre-pour inspection is the only record
  • Bracing, alignment and propping are a real temporary works item that has to be designed and checked
  • External finish is an added trade, and the detailing at openings and junctions needs care
  • Design that ignores the unit module wastes material and slows the build

What is Insulating concrete formwork (ICF) best suited for?

Low-rise housing, self-build and small developer schemesBuildings targeting low heat loss and low air leakage without a separate specialist tradeBasements and retaining walls where the insulation is wanted anywaySchools, care homes and small commercial buildings of simple wall geometrySites with restricted craneage where a lightweight, hand-placed system suits

What plant does Insulating concrete formwork (ICF) need?

  • ICF units, corner units, window and door bucks, and the ties within the units
  • Bracing, walers, alignment gear and props with their working platforms
  • Concrete pump with a hose arrangement that limits free fall, or skip and crane on larger work
  • Reinforcement, spacers and tying equipment
  • Hot-wire or hand tools for cutting units, and conduits, sleeves and fixing plates for cast-in items
  • Levels, plumb and line equipment for continuous checking during the pour

How is Insulating concrete formwork (ICF) quality-checked?

  • Foundation level and line checked, and the starter course set out and fixed before stacking begins
  • Reinforcement, laps, opening steel, conduits and cast-in fixings inspected and recorded before the pour - the last chance to see any of it
  • Bracing and alignment system inspected and signed against the design before concrete is called off
  • Pour layered to the lift heights and rate the temporary works designer set, with the wall walked continuously during placing
  • Plumb and line checked and adjusted while the concrete is still workable, and any joint movement dealt with immediately
  • Bracing released only against the designer's criteria, and the finished wall checked for line, level and opening dimensions before finishes

More site-based mmc - tunnel form, jump form, slipform, icf methods