Ports, Harbours & Marine WorksQuay Walls & Berth Construction - method

Combi-walls

Heavy tubular king piles carrying the load, with lighter sheets spanning between them.

Last updated 2026-09-06

Combi-walls

What is Combi-walls?

A combi-wall is what a sheet-pile wall becomes when the berth gets deeper. Instead of one uniform curtain of sheets, the wall is built from two elements with two jobs. Large-diameter steel tubular piles - the king piles - are driven at regular spacing and carry almost all of the bending and the vertical load. Between them, lighter sheet-pile sections are driven in the interlocks welded to the tubes, and their job is only to retain the soil across the gap and hand the pressure back to the tubes. The result is a wall with far more strength and stiffness than a sheet-pile wall of the same weight of steel, because the material is concentrated where the bending is.

The advantages follow from that. The heavy tube can be driven through ground that would stop a sheet, so the method opens up sites with dense sand, gravel, glacial till or weathered rock where a plain sheet-pile wall would refuse. The tube can also be driven far deeper, which gives the fixity a deep berth needs, and it can take vertical load from a crane rail or a deck if the designer wants it to. The infill sheets stop short of the tube toe, since they only need to retain soil down to dredge level and a little below, so steel is not wasted. Where the tube is filled with concrete and reinforced, additional strength and corrosion life come with it.

The costs are real. Tubes are expensive, they need a big hammer and a big base machine or barge, and the tolerance on driving them is unforgiving because a tube out of position or out of plumb makes the infill sheets impossible to pitch. The interlocks welded to the tubes are a fabrication item that has to be right before the steel leaves the yard. Corrosion protection is the same problem as for sheet piling and is dealt with the same way, by some combination of thickness allowance, coating, cathodic protection and concrete encasement that the designer selects. On most projects the choice between a combi-wall and a relieving-deck quay comes down to the ground: if the tube can be driven and fixed, a combi-wall is usually simpler.

How does Combi-walls work, step by step?

  1. 1

    Step 1: Establish the ground and choose the wall type

    The investigation along the wall line has to be good enough to answer two questions: can a large tube be driven to the depth the design needs, and what fixity will it get there. Dense layers, boulders, obstructions and rockhead level all matter. The designer compares a combi-wall against a plain sheet-pile wall and against a piled relieving deck, and the answer usually turns on retained height and drivability. All the sizing - tube diameter, wall thickness, spacing, driven depth, infill section and any anchor - is the geotechnical and marine engineer's work for that berth.

  2. 2

    Step 2: Fabricate the tubes with their interlocks

    Tubes are supplied or fabricated to length, with interlock sections welded along both sides to receive the infill sheets. That welding is a controlled fabrication activity with its own inspection regime, because an interlock that is out of line or out of tolerance will not thread a sheet on site, and correcting it over water is slow and expensive. Shop coatings are applied at the same stage where the corrosion protection design calls for them, since coating in a yard is far better work than coating on a barge.

  3. 3

    Step 3: Set out and drive the king piles

    Tubes are pitched in a heavy guide frame and driven by impact or vibratory hammer, or drilled and driven where hard strata demand it. Position and plumb are surveyed on every tube, in both directions, because the infill sheets have to thread between them. Driving records - blow counts, energy, penetration - are kept for each tube and reviewed against the drivability assessment. Where a tube refuses high, the marine contractor stops and the designer decides, since a short king pile changes the wall's behaviour.

  4. 4

    Step 4: Thread and drive the infill sheets

    Infill sheets are pitched into the interlocks on the tubes and driven to the depth the design requires, which is generally well short of the tube toe. Threading is the operation that punishes any error in the tubes, so it is done as soon after driving as practical while the survey is fresh and corrections are still possible. Interlock integrity is checked as the sheets go down, and a declutched sheet is dealt with rather than covered up.

  5. 5

    Step 5: Complete the tubes and cast the capping beam

    Where the design calls for it, tubes are cleaned out, reinforced and filled with concrete, which stiffens the wall and adds corrosion life. A reinforced concrete capping beam is then cast along the head of the wall, connecting the tubes and the sheets into a single line and providing the level and alignment for the berth fittings. Where the wall is anchored, walings and tie rods are installed to the designer's arrangement at this stage.

  6. 6

    Step 6: Backfill and dredge in the specified sequence

    The sequence of filling behind and dredging in front is set by the designer and followed exactly, with wall movement monitored as the balance changes. Filters and drainage go in behind the wall so that water pressure is relieved and fine material cannot wash through the interlocks. The berth pocket is dredged in controlled stages and surveyed, with overdredging treated as a defect because it removes support the wall was designed to have.

  7. 7

    Step 7: Install the corrosion protection system

    Coatings are made good where driving has damaged them, encasement is placed at the levels specified, and the cathodic protection system - sacrificial anodes or impressed current - is installed, connected and commissioned with its readings recorded. Baseline thickness measurements are taken on the tubes and the sheets at the levels the port authority will re-measure in service. This is the part of the project most often squeezed by programme, and it is the part that decides how long the berth lasts.

  8. 8

    Step 8: Fit out, prove and hand over

    Fenders, bollards and quick-release hooks are installed and proof loaded, crane rails are set where the berth carries rail-mounted cranes, and services and apron surfacing are completed. A multibeam survey of the pocket, a topographic survey of the apron, the as-built wall line and the full driving and corrosion protection records are issued together, along with the movement monitoring baseline the port authority will read against.

What are the benefits of Combi-walls?

  • Far greater strength and stiffness than a plain sheet-pile wall for a similar weight of steel
  • Tubes can be driven through dense or obstructed ground that would refuse a sheet
  • Suits greater retained heights and deeper berths without moving to a relieving deck
  • King piles can carry vertical load from crane rails or a deck where the designer wants that
  • Concrete infill to the tubes adds stiffness and corrosion life
  • Built with piling plant and a familiar sequence rather than a casting basin and floating cranes

What are the limitations of Combi-walls?

  • Expensive - large tubes, heavy hammers and heavy base plant
  • Driving tolerance is unforgiving because the infill sheets must thread between the tubes
  • Interlock welding is a fabrication risk that has to be caught in the yard, not on the barge
  • Corrosion protection is as demanding as for any steel wall and needs a lifetime regime
  • Noise and vibration from driving large tubes can be unacceptable near sensitive receptors
  • Repair of a damaged king pile in service is difficult and disruptive to berth operations

What is Combi-walls best suited for?

Deep container, bulk and ro-ro berths beyond the reach of plain sheet pilingGround too dense or obstructed for sheets but drivable by a heavy tubeBerths where the wall must also carry vertical load from craneageQuay extensions where marine plant is available but a casting basin is notSites where a piled relieving deck would be slower or more disruptive to build

What plant does Combi-walls need?

  • Large impact or vibratory hammers with heavy leaders or a piling gate
  • Jack-up platform, spudded barge or heavy land crane sized for the tube weight and length
  • Fabrication yard capability for interlock welding, coating and tube lengthening
  • Cleaning, reinforcement and concreting plant for tube infill
  • Dredging plant and barges for the berth pocket, with multibeam survey
  • Welding, coating and cathodic protection equipment for the marine environment

How is Combi-walls quality-checked?

  • Interlock welding inspected and dimensionally checked before delivery to site
  • King pile position, plumb and driven depth surveyed and recorded individually
  • Infill sheet interlock integrity checked during pitching and driving
  • Tube cleanout, reinforcement and concrete records kept where infill is specified
  • Backfill and dredge sequence followed with wall movement monitored throughout
  • Cathodic protection commissioned with recorded potentials, and baseline steel thickness readings taken

More quay walls & berth construction methods